Supply, installation and commissioning of concrete and culverts batching machinery plant contract at KCCA’s Kyanja yard

Brief description of the works

  • To automate and enhance production at KCCA’s drainage and concrete yard in Kyanja

  • To promote efficiency and output to meet Kampala city’s needs

  • To extend training to KCCA’s staff and technicians on usage of the new machinery

  • To ensure value for money and timely execution of the contract for our client





Project Info

  • Start Date :

    1st Feb 2021

  • Duration :

    8 months

  • Client :

    Kampala Capital City Authority (KCCA)

  • Sector :

    Infrastructure

  • Partner :

    Seka & Charl Ltd

  • Beneficiaries :

    Engineering Dept KCCA

We work above and beyond what is expected to make sure our customer and our company is 100% protected by obeying all of Uganda’s safety, labor and construction codes guided by the license board.